Lemon Grove ADU rules allow a unit up to 1,200 sq ft in most residential zones, but the city's code is out of step with state law: HCD found it non-compliant in December 2025, and permits are still filed on paper at City Hall. Here's what the city publishes, what the state flagged, and what you'll pay.
Lemon Grove ADU facts
None of our verified builders is based in Lemon Grove yet; these work across San Diego County. Each holds an active B license with a bond on file, checked with the state on Oct 26, 2026.
Escondido
San Diego
San Diego
San Diego
Chula Vista
San Diego
Lemon Grove's ADU rules are in Municipal Code § 17.24.060, last updated in 2022, and summarized in the city's ADU development standards handout. ADUs and junior ADUs are allowed in the RL, RLM, RM, RMH, RP and CG zones and nowhere else. The handout says it is informational only; the code controls.
| Rule | Lemon Grove |
|---|---|
| Size, new detached or attached ADU | 1,200 sq ft and no more than 100% of the house; 800 sq ft is always allowed |
| Size, junior ADU | 500 sq ft, inside the existing home |
| Minimum size | 150 sq ft |
| Height | Detached: 16 ft, or 18 ft within a half-mile walk of a major transit stop, plus 2 ft for a roof pitch that matches the house. Attached: 25 ft |
| Side, street-side and rear setbacks | 4 ft |
| Front setback | 25 ft, but an ADU may go in the front setback if there is nowhere else on the lot |
| Separation | 10 ft from the house and other accessory buildings, unless that would block an 800 sq ft ADU |
| Design | Same architectural style, exterior materials and colors as the house |
| Entrance | ADUs need an exterior entrance only; a junior ADU needs an exterior entrance and may also have an interior one |
| Owner occupancy | Not required for an ADU; required for a junior ADU, recorded before the permit is issued |
| Parking | None within a half mile of a bus stop or transit station, plus other code exemptions |
A few local details matter when you design. ADUs over 800 sq ft must keep the zone's open space and 15% of the lot in landscaping. The city asks for a map showing the distance to the nearest bus stop or transit center, because that distance decides both parking and the allowed height. And the design rule means an ADU should match the house, so check a catalog or prefab ADU against it early. If you're weighing layouts, see attached vs. detached ADUs and our junior ADU guide.
The state fire marshal's March 2025 map for Lemon Grove shows only Moderate and High zones in the city's area, with no Very High category in its legend. The city had to adopt the map by ordinance, and can add areas but cannot remove or downgrade them. Ask whether your lot is in a mapped zone, since that can change building code requirements.
No. On December 10, 2025, the state housing department sent the city a findings letter saying § 17.24.060 fails to comply with state ADU law, and gave it until January 9, 2026 to respond. HCD listed 15 problems. The ones that most affect homeowners:
The city's current handout already reflects some state rules, such as the 18 ft transit height and front-setback relief. Others it still lists, such as one ADU plus one junior ADU per single-family lot.
Lemon Grove has one pre-approved design so far: a 797 sq ft detached ADU by YWR Architects, with two bedrooms, one bathroom, a 112 sq ft porch, and stucco or wood-siding exterior options. It is drawn to the 2025 California codes. Architects and designers can submit their own plans; the city's ADU page says they must include architectural plans and structural drawings and calculations that aren't tied to one site.
The city doesn't say whether the plan is free to use, so ask the architect. For other options in the region, see our guide to pre-approved ADU plans in San Diego.
Lemon Grove doesn't publish an ADU fee estimate. These are the line items we could confirm in the city's FY2025-26 master fee schedule and the school districts' pages. The schedule doesn't say which of them the city charges on an ADU, so ask for an estimate before you apply.
| Fee | Amount | Notes |
|---|---|---|
| Building permit | Based on project valuation | Plan check adds 89.25% of the building permit fee |
| Storm water surcharge | 5% | Of total permit and plan check fees |
| Transportation fee (RTCIP) | $3,047.57 | Per new residential housing unit; ask whether it applies to your ADU |
| Sewer connection (Lemon Grove Sanitation District) | $3,509 | Per equivalent dwelling unit |
| Annual sewer service charge | $674.86 | Per equivalent dwelling unit, occupied residential |
| School fees | $3.21/sq ft + $1.20/sq ft | Lemon Grove School District plus Grossmont Union High School District; none if 500 sq ft or less |
| Water | Set by Helix Water District | The city lists Helix capacity and connection fees as non-city fees |
State law limits several of these. A city can't charge impact fees on an ADU under 750 sq ft, and above that the fee must be proportional to the main house. For utilities, state law bars new connection or capacity charges on most ADUs converted from existing space, and requires any charge on a new ADU to be proportionate to its burden on the system. Lemon Grove School District's fee page lists $3.21 per sq ft, effective July 13, 2024, and says the two districts split the state's maximum fee, 62% to Lemon Grove and 38% to Grossmont. A 750 sq ft ADU would pay about $3,308 in school fees at the current posted rates.
Fees are a small slice of the total. For build costs, see what an ADU costs in San Diego, try the ADU cost calculator, or read about ADU financing.
Lemon Grove still takes building permits only in person, on paper. The Building Division doesn't accept online applications or digital plans. Here's the process the city describes:
Lemon Grove doesn't issue a separate certificate of occupancy; the signed inspection card serves as one. Once your application is complete, state law gives the city 60 days to approve or deny it. The city's handout lists what to put on the title page and site plan to cut down on resubmittals, including a table of every structure's square footage and the landscape percentage.
Demand is steady. The city's housing element reports 8 ADUs permitted in 2019 and 11 in 2020, with 40 applications in 2020, and sets a goal of 15 ADU permits a year, 120 by 2029. Before you sign, read how to hire an ADU contractor, check a contractor's license, and compare verified ADU builders in San Diego County.
For a unit built without permits before January 1, 2020, the city's ADU page explains that under AB 2533 it can't deny a permit unless fixing the unit is needed to correct conditions that would make the building substandard, can't penalize you for the unpermitted unit, and generally can't charge impact or connection fees. The city posts a substandard housing checklist of those conditions. You may hire a licensed contractor for a confidential inspection before you apply. The handout adds that older permitted accessory rental dwelling units (ARDUs) are treated as ADUs.
General information, updated Oct 26, 2026. Rules and fees change; confirm with the Lemon Grove permit office before you rely on them.