ADU construction: the process step by step, with inspections

ADU construction follows the same order as building a small house: site work, foundation, framing, rough-ins, insulation, drywall, finishes and a final inspection, with a city inspector signing off on each stage before it gets covered up. Here's what happens at each step, how long the build takes and how to pay for it without getting ahead of the work.

Fact-checked against 14 sourcesUpdated Oct 26, 2026

Single-story house under construction with wall framing and roof trusses in place

ADU construction process at a glance

The table below follows a new detached ADU on a slab, the most common case. Inspection names come from the City of San Diego's list of inspection types; other California cities use similar stages under the same state building code. The order matters because each inspection has to pass before the work is covered by the next layer.

ADU construction steps and the inspection that closes each one
StepWhat gets builtInspection before moving on
1. PreconstructionPermit issued, site fenced, utilities locatedPreconstruction meeting, if your permit requires one
2. Site prep and undergroundGrading, trenches, sewer, water and electrical linesUnderground
3. FoundationForms, rebar, anchor bolts, then concreteFoundation
4. Framing and dry-inWalls, roof, sheathing, windows, doors, roofingExterior wall framing and roof
5. Rough-insPipes, wiring, ducts or mini-split lines inside the wallsAll frame and rough
6. InsulationWall and ceiling insulationInsulation
7. DrywallGypsum board hung, before tapingLath or gypsum board, plus a shower pan water test
8. Finishes and finalCabinets, flooring, fixtures, paint, meters, solarFinal (approval to occupy)

Your builder typically schedules the inspections and meets the inspector on site. If an inspection fails, the inspector leaves a correction notice, the crew fixes it and the inspector comes back. That loop is normal, but too many of them is a sign of a sloppy crew.

Before the ground breaks

Physical construction is the last third of the project. Before it starts you need a design, a permit and a signed contract. Those phases are covered in their own guides:

Once the permit is issued, the clock runs. In the City of San Diego, a permit is void if work doesn't pass a real inspection within one year of issuance, or if work stops for 180 days after it starts. A permit for a house or its accessory structures expires three years after issuance. Don't pull a permit until your builder can start.

Some permits require a preconstruction meeting with the city before any work begins, for issues like coastal exemptions, height, historical resources or storm water. Your permit card will say if yours does.

Site prep and underground work

The crew fences the work area, sets up a portable toilet and locates existing underground lines. Then comes demolition (an old shed, a patio, a tree), grading and the trenches that carry sewer, water and power from the main house or the street to the ADU.

Pipes and conduit go in while the trenches are open. The city's underground inspection happens before backfill, and systems that need a pressure or water test must be under test when the inspector arrives.

This stage is where budgets slip. Snap ADU's sitework cost breakdown lists a separate SDG&E meter at $10,500 to $15,000, retaining walls at $20,000 to $30,000 or more, $10,000 to $20,000 for a lot that slopes 2 to 4 feet, and about $5,000 for a sewer pump when the ADU sits below the sewer line. Our ADU utilities guide covers meters, panels and sewer connections, and ADU in the backyard covers access and placement.

Noise rules set the working hours. In the City of San Diego, building work that makes disturbing noise is barred between 7 p.m. and 7 a.m., on Sundays and on most legal holidays unless the city issues a noise permit. A friendly note to your neighbors before demolition costs nothing.

Foundation

A new detached ADU typically sits on a concrete slab with thickened edges, or on a raised floor over footings. The crew digs the footings, builds the forms, ties the rebar and sets the anchor bolts and hold-downs that will tie the walls to the concrete. Plumbing that runs under a slab is placed first.

The foundation inspection comes after excavation, forms, reinforcing steel and hardware are in place, and before the pour. Once the concrete is down, mistakes are expensive to fix, so this is a good inspection for you to be at. On a raised floor, the city also inspects the floor framing and any rough plumbing or wiring under it before insulation or subfloor goes on.

If your engineer calls for them, a certified special inspector or testing lab may check concrete or welds, and the engineer of record may make structural observations. Those are in addition to the city inspections, not a replacement.

Framing and dry-in

Framing is the fastest-looking stage: walls can go up in days, then the roof framing or trusses and the sheathing. Windows, exterior doors and flashing follow, then the roofing and a weather barrier. The goal is to get the building “dried in” so rain can't reach the interior.

San Diego inspects exterior wall framing and the roof system as separate steps. Exterior framing is checked once doors, windows and penetrations are flashed; the roof is checked layer by layer. On a two-story ADU the second floor adds another round of framing and inspection.

Walk the framing before it's covered. This is the last time you'll see the bones of the building. Check outlet and switch locations, window heights, blocking for grab bars, TV mounts and kitchen cabinets, and where the shower valve sits. Changes now cost a little. After drywall they cost a lot.

Rough plumbing, electrical and mechanical

With the frame up, each trade runs its lines through the walls and ceiling: drain and supply pipes, electrical wiring and boxes, the subpanel, ducts or mini-split refrigerant lines and the bath and kitchen exhaust.

Everything comes together at the all frame and rough inspection, which looks at the finished framing plus the electrical, mechanical and plumbing work in one visit. Insulation can't go in until it passes.

Insulation, energy checks and drywall

Once the building is weather-tight, insulation goes into the walls and ceiling and gets its own insulation inspection. The city also wants a certificate of compliance on file before final. Then drywall goes up, and the inspector checks it before taping. A shower pan water test is part of that visit.

California's energy code adds third-party testing. Mini-split systems may require field verification and diagnostic testing by a certified rater, and vented range hoods must be verified for airflow and noise rating. Since January 1, 2026, the Energy Code Compliance (ECC) program has replaced the HERS program for this work, and HERS raters are recognized as ECC raters. Your builder hires the rater; the paperwork has to be complete before final. See ADU solar and Title 24 for what the energy code requires.

Finishes and the final inspection

Finish work takes longer than most people expect: tape and texture, paint, cabinets, counters, tile, flooring, doors and trim, then plumbing fixtures, lights and appliances. Outside, the crew finishes siding or stucco, gutters and any flatwork, and restores the yard they dug up. Our ADU kitchen and bathroom guide covers what those rooms must include.

A new detached ADU must have solar panels to meet the energy code's prescriptive path, unless an exception applies; an attached ADU counts as an addition and doesn't. Solar and any new meter involve SDG&E as well as the city, so ask your builder early when they'll be scheduled.

The final inspection happens only after every other approval on the permit is complete. In San Diego, passing it is your approval to occupy. Before you make the last payment, walk the unit with your builder and write a punch list of anything unfinished or damaged.

ADU construction timeline

Snap ADU's November 2025 timeline guide, written from its San Diego projects, gives these ranges:

ADU construction timeline by phase (Snap ADU, Nov. 2025)
PhaseTypical lengthWhat drives it
Design2 to 5 monthsDesign complexity, how fast you make decisions
Permitting3 to 9 monthsYour city, number of correction rounds
Construction5 to 10 monthsUnit size, stories, sitework, inspection queues, weather
Total10 to 18+ monthsAll of the above

The source gives construction as five to seven months in one section and six to ten in its summary, so plan on the wider range. A two-story unit, a hard-to-reach backyard or extra trades such as stair or metal fabricators push it longer. Inspections add days at every stage, since the crew waits for a sign-off before covering work.

For the full schedule, including how long permits take city by city, see how long it takes to build an ADU.

Paying as the work progresses

California law ties your payments to the construction steps above. The down payment can't exceed $1,000 or 10% of the contract price, whichever is less. After that, the Contractors State License Board says it's illegal for a contractor to collect payment for work not yet done or materials not yet delivered. Each progress payment must be listed in dollars and tied to specific work, and that work must be finished before the payment is due. The board also warns about large charges for “plans” or “permits” before work starts.

A practical way to hold that line is to match each payment to a passed inspection:

Tying ADU progress payments to inspections
Payment due whenProof to ask for
Foundation pouredSigned foundation inspection
Framing and roof completeSigned framing and roof inspections
Rough-ins completeSigned all frame and rough inspection
Insulation and drywall completeSigned insulation and drywall inspections
Final inspection passedFinal sign-off, punch list done, unconditional lien releases

Liens are the other risk. Subcontractors and suppliers who might file a lien must send you a preliminary notice; keep them. The CSLB advises getting a signed conditional release before each payment and an unconditional release afterward, and says you may hold the next payment until you have the unconditional releases for the last one. Joint checks to the contractor and a supplier are another option. To estimate what the whole job should cost, see ADU construction cost by size and what an ADU costs in San Diego.

Payments ahead of work are a warning sign. San Diego homeowners have been left with unfinished ADUs and debt when builders folded mid-project. If your builder asks for money before the stage is inspected, stop and ask why.

Conversions and prefab ADUs

Accessory dwelling unit construction inside an existing structure

A garage conversion, a basement or attic ADU or a junior ADU reuses walls, roof and often the slab, so the early steps shrink. You may still need new footings, a raised floor over a garage slab, new windows and doors, and a sewer line. The rough, insulation, drywall and final inspections still apply. Hidden problems in old framing or a cracked slab are the main source of change orders.

Prefab and manufactured ADUs

With a factory-built unit, the box is made off site while your site crew does the foundation and utility trenches, so two stages run at once. A manufactured-home ADU is installed by a contractor with a C-47 license. The quoted price often leaves out sitework, which Snap ADU's published prices put at about $35,000 on a level lot as of March 2026. See prefab ADUs in California.

Whatever you build, compare verified ADU builders in San Diego and ask each one to walk you through its construction schedule, inspection by inspection. For the broader start-to-finish plan, see how to build an ADU in California.

Common questions

What are the steps of ADU construction?
Site prep and underground utilities, foundation, framing and roofing, rough plumbing, electrical and mechanical, insulation, drywall, finishes and a final inspection. A city inspector signs off on each stage before it is covered up.
How long does ADU construction take?
Snap ADU's November 2025 guide puts construction at about five to ten months after the permit is issued, and the whole project, from design to move-in, at 10 to 18 months or more.
What inspections does an ADU need?
In the City of San Diego the usual sequence is underground, foundation, framing and roof, all frame and rough, insulation, drywall with a shower pan test, and final. Passing the final inspection is your approval to occupy.
How much should I pay an ADU contractor up front?
No more than $1,000 or 10% of the contract price, whichever is less. After that, California law bars contractors from collecting for work not yet done or materials not yet delivered.
Can my ADU permit expire during construction?
Yes. In the City of San Diego a permit is void if work isn't validated by an inspection within one year of issuance or stops for 180 days, and a permit for a house or its accessory structures expires three years after issuance.

Sources

General information, not legal or financial advice. Rules and fees change; confirm with your city's permit office before you rely on them.