How to build an ADU in California, from lot check to move-in

To build an ADU, you make a handful of decisions in a set order: what your lot allows, what kind of unit to build, what you can spend, who will design and build it, and then the permit, the build and the final sign-off. Get the early ones right and the later ones mostly follow. Here's the whole path for a California homeowner, with San Diego numbers.

Fact-checked against 17 sourcesUpdated Oct 26, 2026

A construction crew framing a floor

Steps to build an ADU in California

The construction itself is the part people picture, but most of the expensive mistakes happen before it starts. This table is the map. Each row is covered below, and the sibling guides go deeper on the construction phases and the calendar.

Steps to build an ADU: decisions in order
StageWhat you decideWho usually does the work
FeasibilityWhere a unit can go, how big, how utilities reach itYou, with a builder or designer
TypeDetached, attached, garage conversion or junior ADUYou
Budget and financingTotal you can spend, and how you'll payYou and your lender
Delivery modelDesign-build firm, architect then bid, pre-approved plan or prefabYou
DesignFloor plan, finishes, structural and energy workDesigner or builder
PermitSubmit, answer corrections, pay feesDesigner or builder, for you
BuildChange orders and payments as work is doneLicensed contractor
FinalFinal inspection and approval to occupyContractor and city inspector

For what happens on site from grading to punch list, read the ADU construction process. For how long each stage takes, see how long it takes to build an ADU. If you're still deciding whether you want one at all, start with what an ADU is.

You won't be breaking new ground. California permitted 30,354 ADUs in 2024, more than a quarter of all homes permitted in the state that year, so cities and builders have well-worn processes.

Check what your lot allows

Feasibility answers three questions: where a unit can sit, how big it can be, and what it will take to bring water, sewer and power to it. Most of the answer comes from state law, then your city's code fills in the details.

What California guarantees

  • A by-right approval. ADUs are approved ministerially, without a hearing. On a single-family lot, state law allows a converted ADU, a detached ADU of up to 800 sq ft with 4-foot side and rear setbacks, and a junior ADU inside the house.
  • No owner-occupancy rule for an ADU, so you can rent either the unit or the main house.
  • Limited parking rules. No parking can be required within half a mile walking distance of public transit, for a unit that's part of the house or an existing structure, or within a block of a car-share vehicle.
  • HOAs can't block it. State law voids CC&Rs that prohibit or unreasonably restrict an ADU on a single-family lot. An HOA may set reasonable design standards, but it can't charge fees for approval.

What San Diego adds

In the City of San Diego, the municipal code allows a new ADU from 150 to 1,200 sq ft, with no maximum for conversions of existing space. An ADU 16 feet tall or less needs no interior side or rear setback, except 4 feet in high and very high fire hazard zones. ADUs can be two stories at most in single-family zones, and parking is required only in the Beach Impact Area outside transit priority areas.

Look up your zone in the city's Zoning and Parcel Information Portal (ZAPP), as the city's ADU bulletin suggests. The same bulletin flags the overlays that change a project: lots in the Coastal Overlay Zone usually need a Coastal Development Permit, and fire hazard zones bring extra setbacks.

Then walk the yard with the utilities in mind. How far is the unit from the sewer line, and is it uphill or downhill? Where is the electrical panel? A long trench or a sewer pump changes the budget more than most design choices do. Our ADU utilities guide covers meters, sewer and panel upgrades, and California ADU laws has the full state rulebook.

Two detached ADUs from 2027. Under AB 956, signed in September 2026, single-family lots can have two detached ADUs starting January 1, 2027. If you're designing now and permitting next year, ask your designer to leave room for a second unit.

Choose the kind of ADU

The type you choose sets most of the cost and much of the permit path. Converting space you already have is cheapest per unit; a new detached building gives you the most privacy and rent.

Building an ADU in San Diego: planning ranges by type (Lars Remodel, October 2026)
TypeWhat it isPlanning range
Detached ADUA new, separate building in the yard$250,000–$450,000+
Attached ADUA new unit built onto the house$200,000–$350,000+
Garage conversionAn existing garage turned into a home$150,000–$225,000+
Junior ADUUp to 500 sq ft inside the house$120,000–$200,000+

Those are Lars Remodel's published planning ranges, a builder's figures rather than quotes. For the trade-offs between types, see attached vs. detached ADUs, the garage conversion ADU guide, junior ADU rules and basement and attic ADUs. If space is tight, a small ADU saves fees, and ADU in the backyard covers placement and access.

Budget for building an ADU

Set a total budget before you talk to designers, and include everything: design, fees, sitework and a contingency. The most reliable public San Diego numbers come from builders who publish their prices.

Detached ADU budget by size in San Diego (Snap ADU, March 2026)
SizeTypical all-in costPer sq ft
500 sq ft, 1 bed$300,000$600
750 sq ft, 2 bed$350,000$465
1,000 sq ft, 2 bed$425,000$425
1,200 sq ft, 3 bed$450,000$375

Snap ADU's published prices cover design, permits, basic sitework and utilities, but list extra grading, retaining walls, demolition, added utility work and permit, school and sewer fees as variables on top. Three budget items catch people:

  • City fees. Snap ADU's fee table estimates City of San Diego fees at $10,734 for a 499 sq ft unit and $31,111 for 1,199 sq ft (February 2026). That's a builder's estimate, not the city's schedule. The city exempts the first two ADUs on a lot from development impact fees.
  • Sitework. Snap ADU says $25,000 covers sitework on a flat lot when tie-ins stay on your property. A separate SDG&E meter runs about $10,500, a sewer pump about $5,000, and long trenches up to $200 a linear foot.
  • Property tax. The County Assessor adds the value of the new construction only; your existing house isn't reassessed.

Most homeowners borrow. The common routes are a HELOC, a home equity loan, a cash-out refinance, a construction loan, or a renovation mortgage such as Fannie Mae HomeStyle Renovation or Freddie Mac CHOICERenovation. See ADU financing and ADU grants in California, run your numbers in the ADU cost calculator, and read what an ADU costs in San Diego for the full breakdown. If the unit will be a rental, ADU rental income in San Diego shows the payback math.

Pick who designs and builds it

This is the decision that shapes the rest of the project. There are four common routes:

Ways to build an ADU: delivery models compared
RouteHow it worksBest when
Design-buildOne firm designs, permits and buildsYou want one point of responsibility and cost feedback during design
Architect, then bidA designer draws the plans; builders bid on themYou want design control and bids on identical plans
Pre-approved planYou license a plan the city has already approved; a builder builds itA standard detached plan fits your lot
PrefabA factory builds the unit; a local contractor does the foundation and hookupsYour site has good access for delivery

You don't always need an architect. California lets anyone prepare plans for wood-frame dwellings of up to two stories and a basement, which covers most ADUs. Engineering is a separate question; your plans will still need structural and energy work. Compare the routes in design-build vs. architect, see ADU architects and designers, and read prefab ADUs in California.

Hiring the builder

Whichever route you take, the builder needs the right license. The Contractors State License Board says a B (General Building) contractor can build an ADU, a C-47 contractor can install a manufactured-home ADU, and specialty trades like electricians and plumbers can't run the whole job. It treats an ADU as a home improvement project, so you need a written contract, and you can cancel within three days of signing (five if you're 65 or older). The board also recommends getting at least three bids.

The deposit is capped by law at $1,000 or 10% of the contract price, whichever is less. A builder asking for more up front is a reason to walk away. Compare verified ADU builders in San Diego, check a contractor's license, and read how to hire an ADU contractor before you sign.

Design and plans

Design turns the feasibility answers into a permit-ready plan set. Expect a floor plan, elevations, a site plan, structural drawings and Title 24 energy calculations. The City of San Diego also asks for forms such as a Water Meter Data Card with the application.

Decisions you'll make here:

A pre-approved plan skips most of this. The City of San Diego gives applications that use pre-approved plans a 30-day review, though you still have to license the plan from its owner. In the unincorporated county, the County's free plans are about 85% complete and need site-specific details filled in. See pre-approved ADU plans in San Diego.

The permit

In the City of San Diego, ADU applications go in online through the Development Services application portal, under “Building Construction.” Your designer or builder normally submits and answers the plan-check corrections. State law puts the city on a clock:

ADU permit deadlines under California law
StageDeadlineIf the city misses it
Completeness check15 business days after you applyThe application is deemed complete
Approve or deny60 days after a complete applicationThe permit is deemed approved
DenialWritten list of defects and how to fix themYou can appeal
Pre-approved plan (San Diego)30-day review—

Those deadlines come from the state's ADU handbook, which also notes that you can ask to pause the 60 days, for example while you revise plans. Coastal permits run on their own 60-day clock alongside the building permit. The full walkthrough, including what to submit, is in how to get an ADU permit in San Diego.

Don't pay for plans or permits blindly. The state contractor board warns against paying a contractor for plans unless you know they've paid for them, and suggests checking permit costs with your building department directly.

Construction and inspections

Once the permit is issued, the build is mostly your contractor's job. Yours is to approve changes in writing, pay only for work that's done, and keep an eye on inspections. City inspectors check the work in sequence: underground, foundation, framing, roof, rough plumbing and electrical, insulation, drywall and final. Nothing can be covered up before it's inspected.

Payments should track that progress. CSLB's ADU fact sheet gives a sample schedule:

Sample progress payment schedule to build an ADU (CSLB)
MilestoneShare of contract
Mobilization5%
Demolition and site prep10%
Foundation10%
Framing15%
Rough mechanical, electrical and plumbing15%
Roof and exterior wrap15%
Insulation and drywall10%
Flooring, tile and cabinets10%
Finish mechanical and carpentry5%
Final inspection3%
Keys, after the punch list2%

The same fact sheet tells you to confirm who is handling the underground utilities, since trenching is easy to leave out of a bid, and to get every change order in writing. For the phase-by-phase detail, read the ADU construction process. If you're converting an existing outbuilding, shed to ADU conversions covers what has to be upgraded.

Final inspection and moving in

The last inspection is the one that matters most. In San Diego, final inspection is the approval to occupy, and it comes only after every other approval on the permit is signed off. Under state law, you need a certificate of occupancy before anyone lives in the unit. Hold back the final payment until you have it and the punch list is done.

Before a tenant moves in, know the local rental rules. The City of San Diego requires ADU rentals to be at least 31 days, so short-term vacation rentals are out. If you might sell or refinance later, keep the permit, the final inspection record and the contractor's lien releases together; ADUs and real estate explains why buyers and appraisers ask for them.

How long all of this takes varies with the city and the builder. Snap ADU estimates 10 to 18 months or more from first design to move-in in San Diego. The ADU timeline guide breaks that down by stage.

Common questions

What are the steps to build an ADU?
Check what your lot allows, choose the ADU type, set a budget and financing, pick a design-build firm or a designer, finish the plans, get the permit, build with inspections along the way, and pass final inspection before anyone moves in.
How much does it cost to build an ADU in San Diego?
Snap ADU's March 2026 prices put a detached ADU at about $300,000 for 500 sq ft up to $450,000 for 1,200 sq ft, all-in. Lars Remodel's October 2026 planning ranges run from $120,000 for a junior ADU to $450,000 or more for a detached unit.
How long does it take to build an ADU?
Snap ADU estimates 10 to 18 months or more in San Diego from design to move-in. Once your application is complete, state law gives the city 60 days to approve or deny the permit.
Do I need an architect to build an ADU in California?
Usually not. California lets anyone prepare plans for wood-frame dwellings of up to two stories and a basement, which covers most ADUs. You'll still need structural and Title 24 energy work in the plan set.
Can my HOA stop me from building an ADU?
No. California voids CC&Rs that prohibit or unreasonably restrict an ADU on a single-family lot. An HOA can set reasonable design standards, but it can't charge approval fees or block the city's permit.
Do I have to live on the property to build an ADU?
No. California bars owner-occupancy requirements for ADUs, so you can rent out both the house and the unit. A junior ADU that shares a bathroom with the house is the exception.

Sources

General information, not legal or financial advice. Rules and fees change; confirm with your city's permit office before you rely on them.